St. George Regional Airport's terminal expansion is estimated at about $100 million and would double the building to seven gates. Final drawings are due early 2027; the new control tower should be working by early summer 2027.

Key takeaway: St. George Regional Airport's terminal expansion is estimated at about $100 million and would double the building to seven gates. Final drawings are due early 2027; the new control tower should be working by early summer 2027.

Featured image for St. George Airport Expansion: A $100 Million Terminal With 7 Gates, and a Control Tower Due in Summer 2027 - St. George Regional Airport's terminal expansion is estimated at about $100 million and would double the building to seven gates. Final drawings are due early 2027; the new control tower should be working by early summer 2027.

Photo: City of St. George. The completed St. George Regional Airport control tower, Oct. 6, 2026.

What Is Happening at St. George Regional Airport? Quick Answer

The City of St. George is planning an expansion of the passenger terminal at St. George Regional Airport (SGU), estimated at about $100 million, that roughly doubles the building and brings it to seven gates. Final drawings are expected in early 2027, and the city says it will announce a construction schedule once funding is final. Separately, the airport's new 80-foot air traffic control tower is built, and the city estimates it will be operating by early summer 2027.

Both updates come from the city's airport project pages, last updated Oct. 22, 2026. Here is what those pages say, and what has not been decided yet.

ProjectWhere it stands (city, Oct. 22, 2026)
Terminal expansionAbout $100M estimate; 7 gates; final drawings early 2027; funding not final
Construction managerBig D Construction, under a Construction Manager at Risk contract
RunwayNo extension planned at this time
Control towerStructure finished; estimated operational early summer 2027
Tower operatorRVA, through the FAA Contract Tower Program; part-time tower
2025 passengers431,607, about 35% more than 2024

Why Does St. George Need a Bigger Terminal?

The city's terminal page is blunt: the building "was built for far fewer travelers than it serves today." SGU served 431,607 passengers in 2025, about 35% more than the year before, and the city says some areas of the terminal now reach near capacity at times. The expansion roughly doubles the building's size and takes it to seven gates.

The runway is not part of the project. According to the city, the runway was designed for aircraft much larger than those flying into St. George today, and there is room to lengthen it later if demand requires it.

Who Is Building It, and When Does Construction Start?

The city chose a Construction Manager at Risk process so the builder joins the team during design, and it selected Big D Construction, which the city notes was also the contractor on the Salt Lake City International Airport terminal. The city lists these steps:

  • Master plan: complete. The FAA-approved plan set goals of new routes, larger aircraft and lower fares.
  • Construction manager selected: complete.
  • Final funding: in progress, with Washington County.
  • Design: in progress; final drawings expected early 2027.
  • Phased construction plan: in progress, designed to keep the terminal operating as normally as possible.
  • Bidding the subcontracted work, construction, and opening: upcoming.

There is no construction start date yet. The city says it will share one "once funding is final and our phased construction plan is complete." The city's own milestone list notes that it presented a terminal funding request to a Utah Legislature subcommittee in January 2026. On the county side, the Washington County Commission in July 2026 authorized up to $50 million in sales tax revenue bonds, repaid from tourism-related taxes, that can pay for the St. George Regional Airport expansion, the Dixie Center expansion, or both; the county has not said how the money would be split (see our Dixie Center expansion story). The page also says the materials and colors shown in early images are conceptual only.

When Will the Control Tower Open?

Since opening in 2011, SGU has operated without an on-site tower. The city says pilots coordinate with each other and air traffic is managed remotely from California. The new tower sits midfield beside the runway, and the structure is finished. The city's photo of the completed tower is dated Oct. 6, 2026.

A finished building is not an operating tower, the city explains. Before controllers go on duty:

  • Equipment: the contractor is buying and installing the FAA's Minimum Equipment List. The city says installation is still several months away.
  • Controllers: RVA, the company that will run the tower under the FAA Contract Tower Program, is hiring now.
  • Letters of Agreement between the airport and RVA, then runway, taxiway and sign updates.
  • FAA certification is the final step.

The current estimate is early summer 2027, and the city will announce a firm date once the FAA sets the certification schedule. It is planned as a part-time tower, with hours to come. The Utah Legislature provided $15 million for construction, with FAA support for some equipment; Layton Construction won the construction contract in July 2025, and the groundbreaking was Aug. 11, 2025. Nothing about current flights changes while the tower is being finished.

What Else Is Changing Around St. George?

The airport work is one of several big public projects on the south end of town. UDOT's I-15 widening is under way (see our I-15 and Bluff Street construction guide), the city council recently approved an oversight contract for the new Exit 5 interchange (our Nov. 5 council report), and Washington County is hiring a builder for the Dixie Convention Center expansion. For travel planning, see our St. George visitors guide.

Frequently Asked Questions

How much will the St. George airport expansion cost?

The City of St. George estimates the terminal expansion at about $100 million. Funding comes from several sources, and the city says the airport is working with Washington County to secure the final pieces.

How many gates will St. George Regional Airport have?

Seven. The city says the expansion roughly doubles the size of the terminal and brings it to seven gates.

When will the St. George airport control tower open?

The city's current estimate is early summer 2027. The tower building is finished; equipment installation, controller hiring, agreements, airfield marking updates and FAA certification still have to happen. A firm date will be announced once the FAA certification schedule is set.

Is the St. George airport runway being extended?

Not at this time. The city says the runway was built to handle aircraft much larger than those serving SGU today, and there is room to lengthen it if demand ever requires it.

Will the St. George airport close during construction?

The city's goal is to keep the terminal operating normally as much as possible, using a phased construction plan that is still being developed.

How many passengers used St. George Regional Airport in 2025?

431,607, about 35% more than in 2024, according to the city.

Sources: City of St. George, SGU Terminal Expansion (updated Oct. 22, 2026); City of St. George, SGU Tower Construction (updated Oct. 22, 2026); Washington County, Notice of Bonds to be Issued for Airport Expansion Project and Dixie Center Project (July 16, 2026).

About the Author

SGWOM Editorial Team
Community News
darrin@sgwom.com

Featured in This Article

Dixie Convention Center

Event Venues • St. George

The Dixie Convention Center sits off I-15 at Dixie Drive and opened on this site in 1998. Its 46,550-square-foot Exhibit Hall divides into four sections and holds 240 booths, alongside a 13,205-square-foot Ballroom, the Garden Room, a 178-seat auditorium and smaller meeting rooms. Heritage Catering cooks in house, and the Rosenbruch World Wildlife Museum shares the building.

(435) 301-7770
1835 S Convention Center Dr
For business owners

Reach Southern Utah readers

Advertise on St. George Word of Mouth with a sponsorship plan or a social media advertising package.

Stay in the loop after dark

Get Southern Utah's local news, events and businesses delivered to your inbox every Friday.